HS2: Cost of London-to-Birmingham leg of proposed new railway a third higher than previously estimated
Exclusive: The link was forecast at £21.4bn at 2011 prices - it is now approaching £30bn
The cost of the London-to-Birmingham leg of Britain’s proposed new railway, High Speed Two (HS2), is approaching £30bn – a third higher than previously estimated.
The team behind the project, HS2 Ltd, has been asked to submit updated costs of the railway’s first phase to the Treasury ahead of the Comprehensive Spending Review (CSR) later this month.
Previously, the London-to-Birmingham link was forecast at £21.4bn, but this was at 2011 prices. The new estimate is designed to reflect better what will have been spent at real prices when the first phase starts carrying passengers at speeds of up to 250mph in 2026. This figure is understood to be in the high twenties of billions.
Known as the “out-turn cost”, it takes account of the rising cost of construction which is being inflated by shortages of building materials and skilled engineering and project management staff. This construction inflation is higher than the general RPI and CPI measurements of inflation, which partly explains the huge increase in the price tag.
It is understood that the cost of the entire railway, including the trains and the phase two link from Birmingham to Leeds and Manchester, is likely to be £70bn to £80bn, up from £50bn in 2011 prices.
The project’s supporters argue the revised cost does not mean the budget has increased, because it is the same amount adjusted to take account of economic changes as the project develops. The Department for Transport (DfT) has also claimed that every £1 of public money spent on HS2 will provide £2 of benefit to the wider UK economy, and many people working on HS2 believe this to be a conservative estimate that plays down the railway’s boost to the country.
But anti-HS2 campaigners are furious at both the amount of public money being spent on the railway and the fact that it will carve through the English countryside. HS2 has already been hit by cost over-runs: in 2013, HS2 Ltd admitted it had got its sums wrong, increasing phase one’s budget alone by more than £5bn.
A spokesman for the Stop HS2 campaign said that the new price estimate proved the project is a “white elephant”. Ministers are already under pressure from Conservative backbenchers whose constituencies are located along the HS2 route to axe the project. They are likely to vote against a bill authorising HS2’s construction when it reaches the floor of the House of Commons next year.
A source who has worked on HS2 added the project’s costs means other transport projects will be squeezed during the 2020s. The source added: “The DfT is not a protected department [from spending cuts]. Somebody’s going to have to find £25bn if HS2 ends up costing around £75bn - and that means roads or rail will have to be cut.”
The source added it is “a logical planning assumption that HS2 will be flogged” to the private sector to run it shortly after the second phase is completed in the 2030s. It is understood there have been some informal discussions at HS2 Ltd on future ownership, which could see foreign companies run the railway.
Industry sources believe HS2 will ultimately be sold to the private sector in concessions lasting around 30 years, as happened at HS1, which links London to the Channel Tunnel. Two Canadian pension funds, Borealis Infrastructure and the Ontario Teachers’ Pension Plan, paid £2.1bn in 2010 to run HS1 until 2040.
HS2 is a much longer line and could be sold in up to three separate concessions, another source suggested, which could help recoup some of the project’s massive cost.
The Stop HS2 spokesman said: “These figures show that since HS2 was first announced in 2010, there has been a near doubling of the costs, and with trains not due to run for over another decade, who knows where the cost of this white elephant will end up?
“A responsible chancellor would be asking serious questions about whether it is really worth it, but instead Mr Osborne is cooking the books to invent benefits which simply aren’t there to make HS2 look more palatable, at the same time as drawing up plans to flog it off the private sector at a fraction of the cost.
“If HS2 was really worth it, investors would be lining up to build it. The fact they are not shows this is nothing more than a vanity project, the costs of which will continue to spiral.”
A spokesman for HS2 said: “HS2 Ltd cannot comment on speculation around the content or outcomes of the spending review.”
Comments
Share your thoughts and debate the big issues
Please be respectful when making a comment and adhere to our Community Guidelines.
You can find our Community Guidelines in full here.
Please be respectful when making a comment and adhere to our Community Guidelines.
You can find our Community Guidelines in full here.
Follow comments
Vote
Report Comment
Subscribe to Independent Premium to debate the big issues
Want to discuss real-world problems, be involved in the most engaging discussions and hear from the journalists? Start your Independent Premium subscription today.
Already registered? Log inReport Comment
Delete Comment
About The Independent commenting
Independent Premium Comments can be posted by members of our membership scheme, Independent Premium. It allows our most engaged readers to debate the big issues, share their own experiences, discuss real-world solutions, and more. Our journalists will try to respond by joining the threads when they can to create a true meeting of independent Premium. The most insightful comments on all subjects will be published daily in dedicated articles. You can also choose to be emailed when someone replies to your comment.
The existing Open Comments threads will continue to exist for those who do not subscribe to Independent Premium. Due to the sheer scale of this comment community, we are not able to give each post the same level of attention, but we have preserved this area in the interests of open debate. Please continue to respect all commenters and create constructive debates.